The part that actually controls your schedule isn't the construction, it's the cabinets. Here's what a realistic timeline actually looks like.
A cosmetic kitchen refresh, new hardware, paint, updated fixtures, can be done in 2-5 weeks. A mid-range remodel with new cabinets and countertops typically runs 8-12 weeks. A full gut renovation with structural changes runs 3-6 months. The difference between those numbers almost never comes down to how fast the crew works.
Cabinet manufacturing lead time runs 4-8 weeks in most cases, and that clock starts the day you finalize your selection, not the day demo begins. If cabinets get ordered late because a decision took longer than expected, everything downstream shifts with it. The single biggest thing you can do to keep a kitchen remodel on schedule is finalize cabinet selections early, before demo day, not during it.
Any work touching electrical, plumbing, or structure, relocating utilities, removing a wall, upgrading an electrical panel, needs a permit in Florida. Cabinet or countertop replacement alone usually doesn't. Skipping a required permit isn't just a compliance issue: unpermitted structural work can void insurance coverage for related damage later.
The most common schedule-killer isn't a supply delay, it's a layout decision that gets revisited mid-project after cabinets are already ordered. Getting the layout and the full material list locked before ordering anything is worth the extra week upfront. It's much cheaper than a mid-project change order.
Sources: Regional Tampa Bay contractor timeline data, Angi.